TRAFFIC TROUBLES: Summerlin Parkway construction

Posted at 1:09 PM, Jul 18, 2016
and last updated 2016-07-18 23:27:21-04
Construction of a cable barrier safety rail system in the Summerlin Parkway median progresses with new hours of 5 a.m. to 3 p.m. for daytime left lane closures from Town Center Drive to the 215 Beltway. 
 
Nighttime work in the Summerlin Parkway median from Buffalo Drive to Town Center Drive is also being done. The left lane in both directions will remain closed in the work areas from 7 p.m. to 6 a.m. Sunday evenings to Friday mornings through mid-August. 
 
Phase 3 work in the median from Town Center Drive to the the 215 Beltway is planned to begin in mid-August and continue for approximately two months. Work hours during this phase are expected to be from 5 a.m. to 3 p.m.